Prince 2 - Foundation

14%

Question 41

Which is a purpose of the Managing Product Delivery process?
Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package
Provide a controlled link between the Project Manager and the Team Manager(s)
Enable the Project Board to request updates to the current Team Plan
Establish solid foundations for the project




Answer is Provide a controlled link between the Project Manager and the Team Manager(s)


Question 42

From whom does a Team Manager obtain approval for a completed product?
Project Manager
Project Support
The authority defined in the Product Description
Senior Supplier




Answer is The authority defined in the Product Description

Appendix A 17.1 - Product description ..."define the people or skills required to produce, review and approve the product"

Question 43

Which is an objective of the Managing Product Delivery process?
Sign-off completed Work Packages
Ensure the Business Case is kept under review
Report progress to the Project Board
Ensure that work on products is authorized and agreed with the team




Answer is Ensure that work on products is authorized and agreed with the team


Question 44

What process aims to ensure accurate progress information is provided to the Project Manager?
Starting up a Project
Managing a Stage Boundary
Managing Product Delivery
Directing a Project




Answer is Managing Product Delivery


Question 45

Which process covers the work done by external suppliers who may NOT be using PRINCE2?
Closing a Project
Managing a Stage Boundary
Managing Product Delivery
Directing a Project




Answer is Managing Product Delivery


Question 46

Which two roles are linked by the Managing Product Delivery process?
Corporate or programme management and Project Board
Project Board and Project Manager
Project Manager and Team Manager
Team Manager and external supplier




Answer is Project Manager and Team Manager


Question 47

What is the collective name for individuals or groups who may be affected by a project?
Customers
Project Support
Stakeholders
Team members




Answer is Stakeholders


Question 48

Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?
Create a separate Project Board to manage the supplier elements of the project
Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project's stages.
Create user and supplier groups
Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board




Answer is Create user and supplier groups


Question 49

When should the Project Board refer to corporate or programme management for a decision?
The stage requires resources
It is forecast that project level tolerance will be exceeded
The Senior Supplier or Senior User needs to be changed
Any request for change needs to be approved




Answer is It is forecast that project level tolerance will be exceeded


Question 50

Identify the missing words in the following sentence.

At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.
Stage Plan
Communication Management Strategy
Follow-on action recommendations
Quality Management Strategy




Answer is Communication Management Strategy


< Previous PageNext Page >

Quick access to all questions in this exam