Prince 2 - Foundation

20%

Question 61

Which is NOT included in the PRINCE2 definition of a project?
A project is a temporary organization
A project's purpose is to deliver one or more business products
A project is part of 'business as usual'
A project is based on an agreed Business Case




Answer is A project is part of 'business as usual'


Question 62

Identify the missing words in the following sentence:

A project is [ ? ] organization that is created for the purpose of delivering business products.
a corporate
a temporary
an external
a technical




Answer is a temporary


Question 63

Identify the missing word in the following sentence:

The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.
Principles
Themes
Processes
Techniques




Answer is Principles


Question 64

Which is NOT one of the PRINCE2 integrated elements?
Tailoring PRINCE2 to the project environment
The processes
The products
The themes




Answer is The products


Question 65

Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?
Specify the desired result
Provide the resources and skills to deliver the desired result
Ensure the technical integrity of a project
Develop a project's products




Answer is Specify the desired result


Question 66

Which is a benefit of using PRINCE2?
Enables the management of projects as well as of 'business as usual' activities
Can be tailored by leaving out elements of the method for some projects
Can be applied to any type of project
Avoids the need to involve corporate or programme management




Answer is Can be applied to any type of project


Question 67

Which is a benefit of using PRINCE2?
Is a method specifically designed for technical projects
Provides for the efficient and economic use of management time
Includes many of the proven planning techniques, such as critical path analysis
Can be used to manage both projects and programmes




Answer is Provides for the efficient and economic use of management time


Question 68

Which does NOT reflect the PRINCE2 principle of continued business justification?
There must be a justifiable reason for starting a project
The business justification drives decision making
If a project is no longer forecast to deliver a financial benefit, it should be stopped.
If a project can no longer be justified, it should be stopped




Answer is If a project is no longer forecast to deliver a financial benefit, it should be stopped.


Question 69

Which characteristic distinguishes a project from regular business operations?
Produces benefits
Introduces business change
Manages stakeholders
Incurs cost




Answer is Introduces business change


Question 70

Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?
Change
Cross-functional
Unique
Risk




Answer is Cross-functional