Which is a minimum requirement for applying the plans theme?
The project must have at least two management stages
The team managers in the project must prepare team plans
Scope tolerance must be prioritized using MoSCoW
The project plan must be presented as a Gantt chart
Answer is The project must have at least two management stages
The Team plan is not mandatory
Question 168
Which level of management sets the project level tolerances?
Project board
Team manager
Corporate, programme management or the customer
Project manager
Answer is Corporate, programme management or the customer
As part of management by exception, corporate or programme management will have set project level tolerances. The project board need to agree stage level tolerances and optionally the project manager may set tolerances at work package level (although this may not need to be done at this point in time).
If a project is part of a programme, which 'starting up a project' process activities are MOST likely to be reduced or eliminated?
Appointing the project board and producing the project brief
Planning the initiation stage and appointing the project manager
Producing the additional role descriptions and validating the project product description
Verifying the project approach and capturing previous lessons
Answer is Producing the additional role descriptions and validating the project product description
As per 14.5.4.4 from the Prince2 manual; the programme manager should ensure the appointment of the executive and project
manager, prepare the project brief, alert the project manager to any relevant previous lessons and ensure an
initial project management team is appointed.