Question 91

Which is a task of product-based planning?
Identify activities and dependencies
Write the Project Product Description
Prepare the Work Packages
Produce Product Status Accounts




Answer is Identify activities and dependencies

PRINCE2® recommends the following steps for product‐based planning:
• Designing a plan
• Defining and analysing the products
• Identifying activities and dependencies
• Preparing estimates
• Preparing a schedule
• Documenting a plan
• Analysing risks to a plan

Question 92

Identify the missing word(s) in the following sentence:

PRINCE2 recommends three levels of [ ? ] to reflect the needs of the different levels of management involved in a project.
Management strategies
Plan
Stakeholder interests
Time-driven controls




Answer is Plan


Question 93

Identify the missing words in the following sentence:

A purpose of the Plans theme is to [ ? ] the project's plans.
define a coding system to provide a unique identifier for the products within
summarize the results of the quality activities performed on
provide a framework to design, develop and maintain
define the project benefits to be achieved by each of




Answer is provide a framework to design, develop and maintain


Question 94

What is the first task of product-based planning?
Produce the Initiation Stage Plan
Write the Project Product Description
Identify dependencies
Create the product breakdown structure




Answer is Write the Project Product Description


Question 95

Which product identifies the management stages and timescales of a project?
Project Brief
Project Product Description
Project Plan
Initiation Stage Plan




Answer is Project Plan


Question 96

How many tasks does the product-based planning technique describe?
One
Two
Three
Four




Answer is Four

PRINCE2 requires that four products are produced and maintained:

1. Project product description :A description of the overall project's output, including the customer's quality expectations, together with the acceptance criteria and acceptance methods for the project. As such it applies to a project plan only.

2. Product description : A description of each product's purpose, composition, derivation and quality criteria.

3. Product breakdown structure : A hierarchy of all the products to be produced during a plan.

4. Plan : Provides a statement of how and when objectives are to be achieved, by showing the major products, activities and resources required for the scope of the plan. In PRINCE2, there are three levels of plan: project, stage and team. In addition, PRINCE2 has exception plans, which are created at the same level as the plan they are replacing.

Question 97

What is shown in a product breakdown structure?
Management stages, major products and control points
In which order the products should be created
The major products that are to be developed in a plan
The resources that are required to develop the products




Answer is In which order the products should be created


Question 98

Which statement applies to Stage Plans?
Always have the same duration as the Project Plan
Are produced at the same time as the Project Initiation Documentation
Assist the Project Manager in the day-to-day running and control of the project
Provide a baseline against which the Project Board monitor overall progress




Answer is Assist the Project Manager in the day-to-day running and control of the project


Question 99

Which is a recommended quality review team role?
Project Manager
Assurance
Project Support
Administrator




Answer is Administrator


Question 100

Identify the missing word(s) in the following sentence:

The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.
controls
products
project management team
stages




Answer is products