Which product is created in the 'starting up a project' process to define and confirm the scope of the project?
Project mandate
Initiation stage plan
Project initiation documentation
Project brief
Answer is Project brief
According to A.19.2 of Prince 2 project brief provides project definition which constrains of: project scope and exclusions, contraints and assumptions.
Question 153
What is the project manager role responsible for?
Approving the completion of each management stage
Ensuring that the project produces the required products
Defining the project-level tolerances
Verifying that the project gives value for money
Answer is Ensuring that the project produces the required products
Question 154
Which theme provides all management levels within the project management team with mechanisms for monitoring and control?
Progress
Change
Organization
Quality
Answer is Progress
Question 155
Which process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
Which product is created in the 'starting up a project' process to define and confirm the scope of the project?
Project mandate
Initiation stage plan
Project initiation documentation
Project brief
Answer is Project brief
According to A.19.2 of Prince 2; project brief provides project definition which constrains of: project scope and exclusions, contraints and assumptions.
Question 157
Which is a minimum requirement for applying the quality theme?
To use lessons to inform quality planning
To use the prescribed approach to quality management
To use external quality standards for quality control
To use user stories to inform the project product description
Answer is To use lessons to inform quality planning
Prince2 Manual section 8.2;
use lessons to inform quality planning, the definition of quality expectations and quality criteria (PRINCE2's
learn from experience principle).