Question 151

Which process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
Directing a project
Managing a stage boundary
Controlling a stage
Starting up a project



Question 152

Which product is created in the 'starting up a project' process to define and confirm the scope of the project?
Project mandate
Initiation stage plan
Project initiation documentation
Project brief




Answer is Project brief

According to A.19.2 of Prince 2 project brief provides project definition which constrains of: project scope and exclusions, contraints and assumptions.

Question 153

What is the project manager role responsible for?
Approving the completion of each management stage
Ensuring that the project produces the required products
Defining the project-level tolerances
Verifying that the project gives value for money




Answer is Ensuring that the project produces the required products


Question 154

Which theme provides all management levels within the project management team with mechanisms for monitoring and control?
Progress
Change
Organization
Quality




Answer is Progress


Question 155

Which process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
Directing a project
Managing a stage boundary
Controlling a stage
Starting up a project



Question 156

Which product is created in the 'starting up a project' process to define and confirm the scope of the project?
Project mandate
Initiation stage plan
Project initiation documentation
Project brief




Answer is Project brief

According to A.19.2 of Prince 2; project brief provides project definition which constrains of: project scope and exclusions, contraints and assumptions.

Question 157

Which is a minimum requirement for applying the quality theme?
To use lessons to inform quality planning
To use the prescribed approach to quality management
To use external quality standards for quality control
To use user stories to inform the project product description




Answer is To use lessons to inform quality planning

Prince2 Manual section 8.2;
use lessons to inform quality planning, the definition of quality expectations and quality criteria (PRINCE2's learn from experience principle).

Reference
http://prince2.wiki/Quality

Question 158

Identify the missing words in the following sentence:

The 'directing a project' process starts when [ ? ] and is triggered by the request to initiate a project.
the 'starting up a project' process is completed
the project mandate has been approved by the project board
the project board has agreed the project strategies
corporate, programme management or the customer have authorized a project




Answer is the 'starting up a project' process is completed

Reference:
https://www.siliconbeachtraining.co.uk/blog/prince2-directing-project-process-dp

Question 159

Which process is used to define how baselines will be established and controlled?
Controlling a stage
Directing a project
Initiating a project
Starting up a project




Answer is Initiating a project

One of the objectives of this process is to define how baselines will be established and controlled.

Reference:
Prince2 manual, 16.2

Question 160

Which risk response is applied on a pain/gain basis?
Share
Accept
Exploit
Enhance