Question 51

Which is NOT a purpose of the Organization theme?
Define a project management team structure
Define the level of tolerance for each level of the project management team
Define the Project Board's responsibility for directing the project
Define which role is accountable for the project's success




Answer is Define the level of tolerance for each level of the project management team


Question 52

Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?
Those with a financial interest in the project
Those who will manage the project on a day-to-day basis
Those who will specify the desired outputs of the project
Those who will create the project's outputs




Answer is Those who will manage the project on a day-to-day basis

There are three primary stakeholders, which are:
• Business sponsors: who endorse the objectives and ensure the project provides value for money.
• Users: who will be using the products to generate benefits, usually after the project is completed.
• Suppliers: who provide the resources and expertise needed to undertake the project work and these can be internal or external

Question 53

Which does the Executive need to ensure is in place before the project is initiated?
All Work Packages are authorized
An understanding of how the project will contribute to corporate objectives
The Project Plan has been approved
The Project Initiation Documentation is complete




Answer is An understanding of how the project will contribute to corporate objectives


Question 54

Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete?
Executive
Senior User
Senior Supplier
Project Manager




Answer is Senior User


Question 55

What product is used to maintain a record of those who have an interest in the project and their information requirements?
Project Plan
Communication Management Strategy
Project Brief
Project Product Description




Answer is Communication Management Strategy


Question 56

Identify the missing word in the following sentence:

A member of the Project Board is responsible for [ ? ] assurance.
quality
supplier
risk
product




Answer is supplier

The project board members each have a specific area of focus for project assurance, namely business assurance for the executive, user assurance for the senior user(s) and supplier assurance for the senior supplier(s).

Question 57

How many roles make up the Project Board?
One
Two
Three
Four




Answer is Three


Question 58

Which of the following statements about stakeholders are true?

1. Someone who thinks they will be affected by a project is a stakeholder on that project.
2. Stakeholders may be internal or external to the corporate organization.
Only 1 is true
Only 2 is true
Both 1 and 2 are true
Neither 1 or 2 are true




Answer is Both 1 and 2 are true

Both are correct. "Any individual, group or organization that can affect, be affected by or perceive itself to be affected by, an initiative". So by perceiving yourself to be affected, i.e. you think to you are affected makes you a stakeholder.

Question 59

Which is one of the six aspects of project performance that needs to be managed?
Progress
Change
Risk
Security




Answer is Risk


Question 60

Which aspect of project performance must be managed to ensure the project's products are fit for purpose?
Benefits
Quality
Risk
Scope




Answer is Quality