Prince 2 - Foundation

34%

Question 111

Which risk response type is appropriate to respond to an opportunity?
Accept
Fallback
Exploit
Transfer




Answer is Exploit


Question 112

Which statement defines a risk?
A certain event occurring in the future that will have a negative impact on the project's objectives
An event that has already occurred that the Project Manager must deal with immediately
An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectives
An uncertain event, or set of events that, should it or they occur, will be automatically escalated to the Project Board for a response




Answer is An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectives


Question 113

Identify the missing word in the following sentence:

The risk response type [ ? ] can be used to respond to a threat and an opportunity.
Avoid
Reduce
Share
Transfer




Answer is Share


Question 114

Which is NOT considered when defining risk tolerance?
A Project Board's attitude towards risk taking
The allocated risk budget
An organization's risk appetite
The amount of risk a Project Board considers acceptable




Answer is The allocated risk budget


Question 115

Which is a responsibility of a risk owner?
Identify risks to the project that might occur in their department
Own and authorize the use of the risk budget to fund risk responses
Manage, monitor and control all aspects of an assigned risk
Determine project risk appetite




Answer is Manage, monitor and control all aspects of an assigned risk


Question 116

Identify the missing words in the following sentence:

The role of [ ? ] is responsible for carrying out a risk response action to respond to a particular risk.
Project Assurance
Project Support
the risk actionee
the risk owner




Answer is the risk actionee


Question 117

Which is a purpose of the Risk theme?
Establish a method for the implementation of continuous improvement during the project
Identify, assess and control problems that have occurred
Provide the Project Board with a time-driven control to capture all project risks
Establish a cost-effective procedure to identify, assess and control risks




Answer is Establish a cost-effective procedure to identify, assess and control risks


Question 118

Which document should record the agreed amount of risk budget for a project?
Project Brief
Project Plan
Risk Management Strategy
Risk Register




Answer is Risk Management Strategy

A risk management approach describes how risk will be managed on the project. This includes the specific processes, procedures, techniques, standards and responsibilities to be applied.
Risk budget is reserved in Risk Management Strategy

Question 119

Which statement describes the 'Implement' step within the recommended risk management procedure?
Take planned action to respond to a risk
Implement the responsibilities for risks defined in the Risk Management Strategy
Assess the proximity of a risk
Identify the level of risks that can be tolerated by the project




Answer is Take planned action to respond to a risk


Question 120

Which is a purpose of the Risk theme?
Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
Establish a cost-effective procedure to identify, assess and control uncertainty
Establish mechanisms to control any unacceptable deviations from plan
Establish mechanisms to manage risks at the corporate or programme level of an organization




Answer is Establish a cost-effective procedure to identify, assess and control uncertainty


< Previous PageNext Page >

Quick access to all questions in this exam