Prince 2 - Foundation

42%

Question 141

How is the tailoring approach defined for a project?
The project board approves the approach
The project board documents the approach
Project assurance approves the approach
Project assurance documents the approach




Answer is The project board approves the approach


Question 142

Which is a purpose of the change theme?
To prevent change to baselined products
To identify, assess and control any potential and approved changes to baselined products
To establish mechanisms to monitor and compare actual achievements against those planned
To assess and control uncertainty




Answer is To identify, assess and control any potential and approved changes to baselined products

Reference:
https://www.greycampus.com/opencampus/prince-2-foundation/introduction-on-prince2-change-theme

Question 143

Identify the missing words in the following sentence:

When proposed changes [ ? ], the change authority must refer the decision back to the project board.
are below the agreed change budget
are objected to by team members
are rejected by the change authority
exceed the agreed change budget




Answer is exceed the agreed change budget


Question 144

Which is a key decision made during the 'directing a project' process?
Select and appoint the project executive
Approve the project manager role description
Confirm that the benefits management approach addresses all expected benefits
Approve the proposed project mandate




Answer is Confirm that the benefits management approach addresses all expected benefits

Per Prince2 Manual section 15. 4. 2 Authorize the project Review and approve the benefits management approach. Confirm it addresses all the expected benefits and meets the needs of corporate, programme management or the customer. is an activity as pert of Authorize the project which happens as part of "Directing a Project" process.

Project Manager role description is approved by Corporate or Program Managment in "Starting up a project" process, therefore option B is not correct answer.

Question 145

What action is taken as part of the 'controlling a stage' process?
1. Create an exception plan
2. Authorize work to be done
3. Take corrective action
4. Obtain approvals for completed products
1 and 2
2 and 3
3 and 4
1 and 4


Question 146

Why can PRINCE2 be applied to any type of project?
Because it provides the project manager with procedures for managing project risks and issues
Because it allows each member of the project management team to fully understand their role and responsibilities
Because it separates the management of the project from the specialist work needed to deliver the products
Because it provides the project manager with a planning procedure to plan the project more effectively




Answer is Because it separates the management of the project from the specialist work needed to deliver the products

In Prince2 Manual Chapter 1 Introduction
PRINCE2 has been designed to be generic so that it can be applied to any project regardless of project scale, type, organization, geography or culture. It achieves this by:
• separating the management of project work from the specialist contributions

Reference:
https://www.prince2.com/uk/prince2-methodology

Question 147

Which is a purpose of a quality register?
To record the quality management approach for a product
To issue a unique reference number for each product
To detail the number and type of quality activities to be conducted
To identify corrective actions that are required after an audit by quality assurance




Answer is To detail the number and type of quality activities to be conducted

Reference:
http://prince2.wiki/Quality#The_Quality_Register

Question 148

Which describes a characteristic of a project?
It maintains business as usual profitability
It provides a quality service to customers
It involves a team with different skills
It enables established and proven best practices




Answer is It involves a team with different skills

2.1one characteristic of project work that distinguish it from business as usual: Cross-functional: A project involves a team of people with different skills working together

Question 149

What is the project manager role responsible for?
Approving the completion of each management stage
Ensuring that the project produces the required products
Defining the project-level tolerances
Verifying that the project gives value for money




Answer is Ensuring that the project produces the required products


Question 150

Which theme provides all management levels within the project management team with mechanisms for monitoring and control?
Progress
Change
Organization
Quality




Answer is Progress

Reference:
https://www.whatisprince2.net/prince2-theme-progress.php

< Previous PageNext Page >

Quick access to all questions in this exam